Over or under budget: reading variance

Tell whether you're over or under plan, and read the Budget position label without mistaking it for a verdict.

In this guide
  1. Prerequisites
  2. What is variance?
  3. Why expense and revenue read in opposite directions
  4. What does Budget position mean?
  5. Example: a manufacturer over on tooling

Prerequisites

  • A budget with a Current figure for at least one category.

What is variance?

Variance is the gap between what RunwayCal sees and what you planned, measured over the period so far. This guide is about reading that gap in RunwayCal; for the general idea of budget versus actual, see the Budget vs Actual guide.

Variance
ItemWhat it meansWhy it matters
Variance (amount)Current minus Budget, both to date.A negative expense variance means Current is below plan; positive means above.
Variance %The variance as a share of the budget to date.Shows the size of the gap. RunwayCal protects it when the budget is zero.

RunwayCal flags the size for you: a bigger percentage gap stands out more than a small one, so the categories that have drifted most are easy to spot.

Why expense and revenue read in opposite directions

The same arithmetic means different things depending on whether the category is an expense or revenue.

Direction of a variance
ItemWhat it meansWhy it matters
Expense, Current below budgetYou've seen less cost than planned.Reads as Under budget. Whether that's good depends on why.
Expense, Current above budgetYou've seen more cost than planned.Reads as Over budget.
Revenue, Current above planProjected committed revenue is above target.Reads as Above plan.
Revenue, Current below planProjected committed revenue is below target.Reads as Below plan.

What does Budget position mean?

The headline Budget position sums up your expense variance in plain words.

Budget position (expense)
ItemWhat it meansWhy it matters
Under budgetCost so far is below plan.A fact about where you stand.
On budgetCost so far matches plan.A fact about where you stand.
Over budgetCost so far is above plan.A fact about where you stand.

Example: a manufacturer over on tooling

Example

Plant tools and software, over budget to date

A manufacturer budgets $40,000 of tools and software for the period so far, and RunwayCal sees $46,000 of cost. The variance is +$6,000, or +15%, so the category reads Over budget and is flagged as a bigger gap worth a look. The label is just a fact: the team still decides whether it was a one-off or a trend.

Tools & software budget (to date)
$40,000
Current (recognized cost to date)
$46,000
Variance
+$6,000 (+15%)
Position
Over budget
Conceptual example. Use reviewed workspace values for an actual decision.